Bernard Venet Sculpture

For this disassembly, we used a 10 ton gantry, a 5K forklift, and a 3 ton chain hoist (attached to the structure of the building in order to keep the top portion upright). We suspended the work with all the equipment simultaneously before using a torch to cut/separate the work in order to lower each piece safely to the ground. Once the work was disassembled and laid flat, it was re-rigged and moved onto a flatbed trailer and transported off site to storage.

The Centrum – Dallas, TX

For management of projects like this, call us.

Specs

Steel
~6,000 – 8,000 lbs

Duration

Planning – 6 weeks
De-Installation – 2 days
Tear down – 8 hours

Resources

10 Ton Gantry Crane
5K Forklift
3 Ton Chain Hoist

project

De-Installation
Fabrication
Transport